Office of the Vice President for Global Communications

Tuesday, September 3, 2013

Angell Hall computing site reopens today

Following its first significant renovation since opening in 1988, the Angell Hall computing site reopens today.

The Board of Regents approved the $4.4 million renovation project during its December 2012 meeting.

The work updated approximately 32,000 gross square feet of space to expand the computing site and provide new furniture, improve accessibility, refurbish the computer classrooms on site, and install a new raised flooring system for maximum future flexibility.

The renovation also included an additional entrance to help improve traffic flow in and out of the computing area, and upgraded mechanical and life-safety systems.

For more information on the renovations, go to www.itcs.umich.edu/sites/angell-reopening.